Agenda item

APP/10/00401 - Land Off New Chester Road, Bromborough, Wirral - Resubmission of Application Ref. APP/2009/6529 - Proposed Replan to Final Phase (Plots 60-99 / 112-122 + 129-146) - Construction of 69No Dwellings together with Associated Works. (Omission of Plots 147 to 192) Original Planning Approval Ref. APP/2007/5272

Minutes:

The Director of Technical Services submitted the above application for consideration.

 

Resolved (11:00) – That the application be approved subject to the following conditions:

1 The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.

2 No development shall take place until samples of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details.

3 No development shall be commenced until full details of soft and hard landscaping have been submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall detail the locations, species and heights of all existing and proposed trees, shrubs and hedge planting and all existing and proposed grassed and hard surfaced areas and any other natural or proposed features.

4 Any trees or shrubs removed, dying, being severely damaged or becoming seriously diseased within five years from the completion of the scheme shall be replaced by trees or shrubs of a similar size and species to those originally required to be planted unless otherwise approved in writing by the Local Planning Authority.

5 All hard and soft landscape works shall be carried out in accordance with the approved details as set out in Condition 3. The works shall be carried out:

- In accordance with a programme to be agreed with the Local Planning Authority;

6 Details of a Method Statement of Arboricultural Works and the Arboricultural site supervision shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of works. The development hereby permitted shall only be carried out in accordance with these approved details.

7 Development works must comply with the Council's Supplementary Planning Guidance for Trees and Development and British Standard Guide for Trees in Relation to Construction Sites (BS 5837) (1991).

8 The development hereby approved shall not commence until a scheme for the translocation of the Bluebells (Hyacinthoides non-scripta) and Purple Ramping-Fumitory (Fumaria purpurea) identified in the Phase 1 Habitat Survey has been submitted to and approved in writing by the local planning authority. The scheme shall include details of the future management of the species and their recreated habitat, together with post-translocation monitoring for a period of 5 years following the translocation. The scheme shall also include details of the site ecologist who will be responsible for undertaking the translocation works. No deviation shall be made from the approved details without the written approval of the local planning authority. The agreed scheme shall be implemented within the first available harvesting/translocation period following the approval of the development hereby permitted.

9 No trees shall be lopped, topped, felled or uprooted without the prior written permission of the Local Planning Authority, nor shall any trees be wilfully damaged.

10 Prior to the commencement of the development, a noise survey, as outlined in Planning Policy Guidance Note 24, shall be submitted to and approved in writing by the Local Planning Authority, in relation to the impact of traffic noise on the future residents of the proposed dwellings. If such a survey identifies any dwelling as being within noise exposure categories B or C then, prior to the commencement of development, a scheme of noise insulation to those dwellings shall be submitted to and agreed in writing by the Local Planning Authority. The approved scheme shall be implemented in full concurrently with the erection of the dwellings to which it relates.

11 No development shall take place within 5 metres of the River Dibbin corridor.

12 Before the development hereby permitted is first commenced, a datum for measuring land levels shall be agreed in writing. Full details of existing and proposed ground levels and proposed finished floor levels shall be taken from that datum and submitted to and approved in writing by the Local Planning Authority, notwithstanding any such detail shown on previously submitted plan(s). The development shall be carried out in accordance with the approved details and retained as such thereafter.

13 No development shall take place until a scheme of land drainage has been submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details prior to the occupation of any of the dwellings hereby approved.

14 Development shall not to be commenced until a Travel Plan has been submitted to and approved in writing by the local planning authority. The provisions of the Travel Plan shall be implemented and operated in accordance with the timetable contained therein and shall not be varied other than through agreement with the local planning authority.

For the avoidance of doubt, such a plan shall include;

a) Access to the site by staff and visitors;

b) Information on existing transport services to the site and staff and visitor travel patterns;

c) Travel Plan principles including measures to promote and facilitate more sustainable transport;

d) Realistic targets for modal shift or split;

e) Identification of a Travel Plan co-ordinator and the establishment of a travel plan steering group;

f) Measures and resource allocation to promote the Travel Plan; and Mechanisms for monitoring and reviewing the Travel Plan, including the submission of an annual review and action plan to the local planning authority.

15 No development shall commence until full details of an emergency vehicular access, including its location, has been submitted to and approved in writing by the Local Planning Authority. The first use of the development shall not commence until such works have been completed in accordance with the Local Planning Authority's written approval and shall thereafter be retained.

16 No development shall commence until a further bat survey has been carried out within the site between the months of October, November and December.  The survey shall be carried out by a suitably qualified ecologist and shall be submitted to and approved in writing by the Local Planning Authority.

17 Before development commences, details of numbers and locations of bat boxes to be erected on the trees within the adjacent woodland(s) shall be submitted to and approved in writing with the Local Planning Authority. Any boxes as may be approved shall thereafter be retained.

18 No development approved by this permission shall be commenced until: -

a) A desk top study has been undertaken to identify all previous site uses, potential contaminants that might reasonably be expected given those uses and other relevant information. Using this information a diagrammatical representation (Conceptual Model) for the site of all potential contaminant sources, pathways and receptors shall then be produced.

b) A site investigation has been designed using the information from (a) above. This should be submitted to, and approved in writing by the local planning authority prior to the investigation being carried out on the site.

c) The site investigation and associated risk assessment have been undertaken in accordance with details approved by the local planning authority.

d) A Method Statement and Remediation Strategy, based on the information obtained from (c) above, have been submitted to and approved in writing by the local planning authority.

e) Work shall be carried out and completed in accordance with the approved Method Statement and Remediation Strategy, referred to in (d) above, and to a timetable agreed in writing by the local planning authority; unless otherwise agreed in writing by the local planning authority.

19 No development approved by this permission shall be commenced until a desk study has been undertaken and agreed in writing by the Local Planning Authority to investigate and produce an assessment of the risk of the potential for on-site contamination. If the desk study identifies potential contamination a detailed site investigation and risk assessment should be carried out to establish the degree and nature of the contamination and its potential to pollute the environment or cause harm to human health. If remediation measures are necessary they will be implemented in accordance with the assessment and to the satisfaction of the Local Planning Authority.

20 A Scheme of acoustic double glazing to all habitable rooms of the proposed new dwellings fronting onto New Chester Road (Plots 141-154) and those facing the existing Lever Faberge site to the North (Plots 60, 61-62, 71-82, 83-84, 85-93, 161, 188-192, 181-187) shall be submitted to and approved in writing by the local planning authority. The approved scheme shall be implemented in full, concurrently with the erection of the dwelling hereby approved.

21 Not withstanding the approved plans all boundary treatment between garden plots; 141-and 151 and New Chester Road shall be constructed of a 1.8m solid timber fence of a minimum thickness of 18mm, details of which shall be submitted to and agreed in writing with the Local Planning Authority prior to the commencement of the development and shall be retained as such thereafter unless otherwise agreed in writing with the Local Planning Authority.

22 The development hereby approved shall be carried out in accordance with the details of the plans received by the Local Planning Department on 8th June 2010

 

 

Supporting documents: