Issue - meetings
Wallasey Town Hall - Means of Escape and DDA Upgrading Works
Meeting: 12/01/2012 - Cabinet (Item 247)
247 Scheme and Estimate Report for Wallasey Town Hall Fire Precaution Works and Refurbishment PDF 81 KB
Additional documents:
- 02 Existing Basement Floor Plan Town Hall, item 247 PDF 45 KB
- 03 Existing Ground Floor Plan Town Hall, item 247 PDF 76 KB
- 04 Existing First Floor Plan Town Hall, item 247 PDF 87 KB
- 05 Existing Second Floor Plan Twn Hall, item 247 PDF 67 KB
- 06 Existing Third Floor Plan Town Hall, item 247 PDF 46 KB
- 07 Existing Roof Plan Town Hall, item 247 PDF 23 KB
- 08 Proposed Basement Plan Town Hall, item 247 PDF 72 KB
- 09 Proposed Ground Floor Plan Town Hall, item 247 PDF 90 KB
- 10 Proposed First Floor Plan Town Hall, item 247 PDF 90 KB
- 11 Proposed Second Floor Plan Town Hall, item 247 PDF 72 KB
- 12 Proposed Third Floor Plan Town Hall, item 247 PDF 145 KB
- 13 Proposed Roof Plan Town Hall, item 247 PDF 36 KB
Minutes:
A report by the Director of Law, HR and Asset Management described the work required to upgrade the access and fire escape arrangements and part refurbishment to Wallasey Town Hall. The costs of the scheme were set out in the report and the Cabinet was asked to consider and approve the proposal.
The Capital Programme included £1,625,000 for works to Wallasey Town Hall including the Civic Hall.
RESOLVED: That
(1) the Scheme and Estimate, as presented, be accepted;
(2) the Director of Law, HR and Asset Management be authorised to seek tenders for the project; and
(3) the Director of Law, HR and Asset Management be authorised to obtain all necessary statutory approvals for the project.