Capital Monitoring Quarter 3 2020/21

Meeting: 01/03/2021 - Council (Item 59)

59 CAPITAL MONITORING QUARTER THREE 2020/21 pdf icon PDF 61 KB

Minute with recommendations and report attached.

Additional documents:

Minutes:

The second item requiring approval was in relation to a revised capital programme for 2020/21.

 

On a motion by Councillor Janette Williamson, seconded by Councillor Anita Leech, it was –

 

Resolved – That the recommendations contained within minute 67 of the Policy and Resources Committee of 17 February, 2021, be agreed in that the following be approved:

 

(1)  additional funding for the schemes referred to in section 3.5 in the report, as follows:

 

  • Birkenhead Park World Heritage Project Team - £0.085m (over a three year period)
  • Connecting Wirral Waters - Detailed Design - £0.610m (over a two year period)

 

(2)  a revised Capital Programme of £86.0million for 2020-21, including the virements referred to in Appendix 3 in the report.


Meeting: 17/02/2021 - Policy and Resources Committee (Item 67)

67 Capital Monitoring Quarter 3 2020/21 pdf icon PDF 124 KB

Additional documents:

Minutes:

Shaer Halewood, Director of Resources, provided an update on the progress of the Capital Programme 2020/21 at the end of December 2020. The report recommended that the Committee agree the revised 2020/21 Capital Programme of £86.0 million which took account of re-profiling, virements, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 2 March 2020.

 

Shaer Halewood reported upon one change to paragraph 3.8.3 in the report, in that the Capital Receipts flexibilities had now been extended until 31 March 2025 which could be used to support expenditure that was ‘Transformational’ in nature.

 

In response to a Member’s comment, Shaer Halewood stated that she would need to investigate further in respect of the virement of funds from Beechwood Leisure Centre to West Kirby Sailing School.

 

On a motion by the Chair seconded by Councillor Anita Leech, it was -

 

A.  RECOMMENDED –

 

(1)  to Council the approval of additional funding for the schemes referred to in section 3.5 in the report, as follows:

 

·  Birkenhead Park World Heritage Project Team - £0.085m (over a three year period)

·  Connecting Wirral Waters - Detailed Design - £0.610m (over a two year period)

 

(2)  to Council the approval of the revised Capital Programme of £86.0million for 2020-21, including the virements referred to in Appendix 3 in the report.

 

B.  Resolved – That this Committee agrees that the outcome of the on-going review and reprofiling of the Capital Programme is reported to Members in the next quarterly capital monitoring report.