Decision details

Conversion of Pensby Park Primary School to Office Accommodation for Children's Services

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

A report by the Director of Children’s Services described the work required to convert part of the former Pensby Park Primary School into office accommodation, the buildings to be vacated, and set out the costs of the scheme.  The Cabinet was asked to consider and approve the proposal.

 

RESOLVED: That

 

(1)  the Scheme and Estimate, as presented, be accepted;

 

(2)  the Director of Technical Services be authorised to obtain all necessary statutory approvals for the project;

 

(3)  the Director of Technical Services be authorised to seek tenders for the project; and

 

(4)  the Director of Children’s Services be requested to use his delegated authority to accept the lowest bone-fide tender and report his acceptance of the tender to the Cabinet in due course, in accordance with the Council’s Procurement Policy.

 

Report author: Director of Children's Services

Publication date: 04/10/2010

Date of decision: 23/09/2010

Decided at meeting: 23/09/2010 - Cabinet

Effective from: 12/10/2010