Decision details

CHANGE PROGRAMME

Decision Maker: Cabinet

Decision status: Awaiting Implementation

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

The Director of Finance presented an update on the change programme agreed by the Cabinet on 7 February 2008.

 

His report identified four key areas for change, culled from over one hundred separate projects considered by Corporate Improvement Group (CIG), and highlighted progress that could be achieved by April 2012.

 

The report detailed where potential savings had been identified from individual projects and noted further that clear management would be essential in driving the programme to achieve efficiencies and improve the processes which underpin how the Council operates. 

 

Members were asked to note progress on the Change Programme and approve the Change Programme 2009/2012.

 

The Leader of the Council requested that the savings and projections be itemised and followed through to implementation.

 

Resolved - That

 

(1)  the progress on the Change Programme 2008-09 be noted; and

 

(2)  the Change Programme 2009-12 be approved

Publication date: 18/12/2008

Date of decision: 10/12/2008

Decided at meeting: 10/12/2008 - Cabinet

Effective from: 30/12/2008

Accompanying Documents: