Decision details
THE OVAL SPORTS & RECREATION CENTRE, BEBINGTON - SCHEME COMPLETION REPORT
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Decisions:
The Director of Regeneration reported upon the final outcome of the successful remodelling of the main sports building at the Oval Sports Centre.
RESOLVED: That
(1) the achievements gained through the remodelling and refurbishment works undertaken at the Oval Sports Centre be noted;
(2) the increased construction costs and fees on the project, as outlined in section 5.0 of the report, be approved and a variation to the Capital Programme to cover the costs, in the sum of £609,685, be agreed; and
(3) the changes and enhancements made to the Council’s tendering procedures for major construction schemes be noted.
Report author: Alan Stennard
Publication date: 09/02/2010
Date of decision: 04/02/2010
Decided at meeting: 04/02/2010 - Cabinet
Effective from: 17/02/2010