Scheme and Estimate Report for Woodlands Primary School to Consolidate Teaching Accommodation
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Scheme and estimate report for remodelling of school accommodation including extension
Decisions:
A report by the Interim Director of Children’s Services described the work required to consolidate teaching accommodation and undertake refurbishment at Woodlands Primary School and set out the estimated costs of the scheme. The scheme formed part of the Children and Young Peoples Department’s Capital Programme approved by the Cabinet at its meeting on 22 July 2010. (Minute No. 82 refers.) The report requested that the Cabinet consider and approve the proposal.
RESOLVED: That
(1) the Scheme and Estimate, as presented, be agreed;
(2) the Director of Law, HR and Asset Management be authorised to seek tenders for the project; and
(3) the Director of Law, HR and Asset Management be authorised to obtain all necessary statutory approvals for the project.
Report author: Director of Children's Services
Publication date: 06/06/2011
Date of decision: 02/06/2011
Decided at meeting: 02/06/2011 - Cabinet
Effective from: 14/06/2011