Decision details
Acceptance of Tender and Award of Contract – A41 Eastham
Decision Maker: Assistant Director: Highways and Infrastructure
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The proposal to improve pedestrian and cycling
facilities on the A41 at Eastham supports the Wirral Council Plan
2025, underpinning the main drivers of sustainable regeneration and
addressing the climate emergency through the promotion of green and
healthy living.
The A41 Eastham STEP Footway/Cycleway Scheme forms part of the
Liverpool City Regions STEP programme by improving transport links
and supporting the delivery of sustainable transport infrastructure
to bring about further growth in our economy, reduce carbon
emissions and support residents to increase levels of active
healthy travel. The scheme will create an off-road shared use
cycle/pedestrian path along the east side of the A41 and will link
the existing shared use cycleway and footway on the A41 to the
north of Eastham Village Road and the newly installed cycle route
improvement work at junction 5 of the M53.
Decision:
Resolved - That
(1) the objection received and the Officers’ response be
noted;
(2) the proposal as shown on attached drawing no.
CO00205643-AMEY-HGN-CPL-DR-C-101 be approved for
implementation;
(3) the tender for the A41 Eastham STEP Footway/Cycleway Scheme
submitted by Cambrianway Ltd to Wirral Council on 5th October 2020
be accepted; and
(4) the award of contract to Cambrianway Ltd, in the sum of
£386,531.00, be approved, subject to contract.
Alternative options considered:
Option 1 - Install project as per drawing no.
CO00205643-AMEY-HGN-CPL-DR-C-101 for
Option 2 - Acquire land to facilitate the widening of proposed
shared use path
Option 3 - Reduce southbound A41 to facilitate the widening of
proposed shared use path
Further detail contained within the attached report.
Publication date: 11/11/2020
Date of decision: 11/11/2020