Provision of a New School at Park Primary School - Scheme and Estimate
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Scheme & Estimate report for replacement
Primary School as part of the government’s Primary Capital
Strategy
Decisions:
The Director of Children’s Services presented a report detailing the work that was required to provide a new primary school and demolition of the existing school at Park Primary School and the costs of the scheme.
Resolved - That
(1) the Scheme and Estimate, as presented, be accepted;
(2) the Director of Technical Services be authorised to seek tenders for the project;
(3) the Director of Technical Services be authorised to obtain all necessary statutory approvals for the project.
Report author: Director of Children's Services
Publication date: 17/04/2009
Date of decision: 09/04/2009
Decided at meeting: 09/04/2009 - Cabinet
Effective from: 23/04/2009
Accompanying Documents: