Decision details
Bidston Moss Viaduct - Full Approval
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decisions:
A report by the Director of Technical Services served to update Members on the latest position in relation to the Department for Transport’s (DfT) consideration of the Major Scheme Business Case submitted in March 2010 and confirmed that the project had now been granted Full Approval to proceed.
RESOLVED:
That the contents of the report be noted and that the Bidston Moss Viaduct strengthening project be granted Full Approval to proceed with associated RFA funding allocation by DfT at the terms indicated within the report.
Publication date: 23/04/2010
Date of decision: 15/04/2010
Decided at meeting: 15/04/2010 - Cabinet
Effective from: 01/05/2010
Accompanying Documents: