A report by the Director of Finance reminded the Cabinet that on 22 July 2010, it had agreed to the terms of a report detailing revised governance and programme management arrangements for the change programme. He presented a further report detailing the budget virements to enable the previous report to be implemented.
RESOLVED: That
(1) £200,800 in 2010-11 and £300,800 in a full year be vired from the Finance Department to Technical Services Department; and
(2) £42,800 of the Efficiency Investment Budget be used to fund a post of Principal Auditor.
Publication date: 26/10/2010
Date of decision: 14/10/2010
Decided at meeting: 14/10/2010 - Cabinet
Effective from: 02/11/2010