Decision details
Docks Link Road Resurfacing - Additional Works
Decision status: Recommendations Approved (subject to call-in)
Is Key decision?: No
Is subject to call in?: No
Decisions:
A report by the Director of Technical Services sought approval of technical variations to the contract for the resurfacing of the A5139 Docks Link Roads in excess of £50,000 or 10% of the tender total.
RESOLVED:
That approval be granted for the variation of the works pursuant to Contract Procedure Rule 16.2 which will increase the contract sum from £832,553 to £1,100,000, which is an increase of £267,447 or 32%.
Publication date: 26/07/2011
Date of decision: 21/07/2011
Decided at meeting: 21/07/2011 - Cabinet
Accompanying Documents: