Resolved - That

 

(1)  the Council be recommended that the current re-engineered 2008-2009 budget detailed in Appendix 1 be agreed, which reflects the virements contained within paragraph 2.2 of the Cabinet report

 

(2)  the revised charges detailed in paragraph 5.8 which should generate an additional £50,000 per annum;

 

(3)  the actions being taken in respect of infrastructure assets be noted and  the proposal to capitalise an additional £500,000 of highways maintenance expenditure be agreed as detailed in paragraph 7 and used to address the shortfalls identified in paragraph.8.1; and

 

(4)  the proposal contained in paragraph 8.1 be noted and the Director of Technical Services explore ways of containing the 2008-2009 deficit within existing resources and report further on the position for 2009-2010 early in the new financial year.

 

Publication date: 17/12/2008

Date of decision: 15/12/2008

Decided at meeting: 15/12/2008 - Council