Issue - meetings

Bidston Moss Viaduct - Final Estimate and Financial Sign Off

Meeting: 15/04/2010 - Cabinet (Item 401)

401 Bidston Moss Viaduct - Full Approval pdf icon PDF 51 KB

Minutes:

A report by the Director of Technical Services served to update Members on the latest position in relation to the Department for Transport’s (DfT) consideration of the Major Scheme Business Case submitted in March 2010 and confirmed that the project had now been granted Full Approval to proceed.

 

RESOLVED:

 

That the contents of the report be noted and that the Bidston Moss Viaduct strengthening project be granted Full Approval to proceed with associated RFA funding allocation by DfT at the terms indicated within the report.