Issue - meetings

Docks Link Road Resurfacing - Additional Works

Meeting: 21/07/2011 - Cabinet (Item 85)

85 Docks Link Road Resurfacing - Additional Works pdf icon PDF 78 KB

Minutes:

A report by the Director of Technical Services sought approval of technical variations to the contract for the resurfacing of the A5139 Docks Link Roads in excess of £50,000 or 10% of the tender total. 

 

RESOLVED:

 

That approval be granted for the variation of the works pursuant to Contract Procedure Rule 16.2 which will increase the contract sum from £832,553 to £1,100,000, which is an increase of £267,447 or 32%.