Issue - meetings

Wirral Coastal Strategy

Meeting: 02/02/2012 - Cabinet (Item 292)

292 Wirral Coastal Strategy - Additional Works pdf icon PDF 80 KB

Minutes:

A report by the Director of Technical Services detailed his decision to extend the contract for the Wirral Coastal Strategy in order to undertake additional works in accordance with Contract Procedure Rule 21.1.1(ii).

 

The additional works and the Wirral Coastal Strategy helped deliver Corporate Objectives under the “Your Neighbourhood” theme to improve the quality of the local environment.

 

The Wirral Coastal Strategy was fully grant aided by the Environment Agency (EA).  The EA had approved the additional expenditure required for the additional works.

 

RESOLVED:

 

That the decision of the Director of Technical Services to extend the Wirral Coastal Strategy contract by the award of additional works to the existing consultant, in accordance with Contract procedure Rule 21.1.1(ii) be noted.