Meeting: 04/02/2010 - Cabinet (Item 319)
319 THE OVAL SPORTS & RECREATION CENTRE, BEBINGTON - SCHEME COMPLETION REPORT PDF 80 KB
Minutes:
The Director of Regeneration reported upon the final outcome of the successful remodelling of the main sports building at the Oval Sports Centre.
RESOLVED: That
(1) the achievements gained through the remodelling and refurbishment works undertaken at the Oval Sports Centre be noted;
(2) the increased construction costs and fees on the project, as outlined in section 5.0 of the report, be approved and a variation to the Capital Programme to cover the costs, in the sum of £609,685, be agreed; and
(3) the changes and enhancements made to the Council’s tendering procedures for major construction schemes be noted.