Agenda item

APP/16/00422: Land Adjacent to St Peters CE Primary School, THURSTASTON ROAD, HESWALL, CH60 4SA - Proposed erection of 4 no. residential units as re-design of APP/14/01341 (Amended plans received amended access and reduce plot to 4 dwellings)

Minutes:

The Assistant Chief Executive submitted the above application for consideration.

 

On a motion by Councillor Elderton and seconded by Councillor Realey it was:

 

Resolved (12:0) That the application be approved subject to the following conditions:

 

1. The development hereby permitted shall be commenced before the expiration of three years from the date of this permission.

 

2. The development hereby permitted shall be carried out in accordance with the approved plans as amended received by the local planning authority on the 5 July 2016 and listed as follows: 001, 002, 003, 004, 005, 006, 007  dated 05.07.16

 

3. No development shall take place until full details of the new access arrangements, including a 2 metre wide footway, have been submitted to, and approved in writing, by the Local Planning Authority.  The footway shall be constructed in accordance with the approved details and before construction of the new dwellings hereby approved is commenced.  The footway shall be retained and maintained permanently thereafter.

 

4. No development shall take place until full details of the road markings relating to school safety have been submitted to and approved in writing by the Local Planning Authority.  The details shall include the amendment of the existing ‘School Keep Clear’ carriageway markings that extend across the proposed access to be replaced by a 'no waiting at any time' on the Thurstaston Road frontage.  The approved road markings shall be completed in accordance with the approved details prior to the first occupation of the development hereby approved.

 

5. No development shall take place until samples of the facing and roofing materials to be used in the external construction of this development shall be submitted to and approved in writing by the Local Planning Authority. The approved materials shall then be used in the construction of the development.

 

6. Prior to first occupation of the development details of a scheme for all boundary treatment shall be submitted to and agreed in writing with the Local Planning Authority. The agreed scheme shall be implemented in full and retained as such thereafter unless otherwise agreed in writing with the Local Planning Authority.

 

7. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2008 (or any subsequent Order or statutory provision revoking or re-enacting the provisions of that Order), no garages, outbuildings or other extensions to a dwelling shall be erected unless expressly authorised.

 

8. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2008 (or any subsequent Order or statutory provision re-enacting or revoking the provisions of that Order), no window or dormer window shall be added to the property unless expressly authorised.

 

9. No development shall take place until full details of soft and hard landscaping have been submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall detail the locations, species and heights of all existing and proposed trees, shrubs and hedge planting and all existing and proposed grassed and hard surfaced areas and any other natural or proposed features. The approved scheme shall be implemented in full in the first planting season following first occupation of the dwellings hereby permitted, unless otherwise agreed in writing by the Local Planning Authority.

 

10. Any trees or shrubs removed, dying, being severely damaged or becoming seriously diseased within five years from the completion of the scheme shall be replaced by trees or shrubs of a similar size and species to those originally required to be planted unless otherwise agreed in writing by the Local Planning Authority.

 

11. No development shall take place until a datum for measuring land levels shall be agreed in writing. Full details of existing and proposed ground levels and proposed finished floor levels shall be taken from that datum and submitted to and approved in writing by the Local Planning Authority, notwithstanding any such detail shown on previously submitted plans. The development shall be carried out in accordance with the approved details.

 

12. No development shall take place until a scheme for the disposal of foul and surface water drainage has been submitted to and approved in writing by the Local Planning Authority. No part of the development shall be brought into use until the drainage system has been constructed and completed in accordance with the approved plans.

 

13. No development shall take place until a Site Waste Management Plan, confirming how demolition and construction waste will be recovered and re-used on the site or at other sites, has been submitted to and approved in writing by the Local Planning Authority. The approved Plan shall be implemented in full unless otherwise agreed in writing with the Local Planning Authority.

 

14. Prior to the first occupation of the dwellings arrangements for the storage and disposal of refuse, and vehicle access thereto, shall be made within the curtilage of the site, in accordance with details to be submitted to and agreed in writing by the Local Planning Authority. The approved details shall be implemented in full unless otherwise agreed in writing with the Local Planning Authority.

 

15. No development shall take place (including any demolition works) until a Construction Management Plan or Construction Method Statement for the demolition and/or construction of the development hereby approved has been submitted to, and approved in writing by, the Local Planning Authority.  The demolition and construction works shall be carried out in accordance with the approved details. 

 

Details submitted in respect of the method statement shall provide for routes for construction traffic, the provision of parking facilities for contractors and visitors during all stages of the development, hours of operation, the provision of a means of storage and/or delivery for all plant, site huts, site facilities and materials and shall provide for wheel cleaning facilities during the demolition, excavation, site preparation and construction stages of the development and/or method(s) of prevention of mud being carried onto the highway.

 