Agenda item

APP/19/00535: HOYLAKE PRESBYTERIAN CHURCH, ALDERLEY ROAD, HOYLAKE, CH47 2AX - Variation of condition 2 of APP/1/00183

Minutes:

The Corporate Director for Economic and Housing Growth submitted the above application for consideration.

 

The Ward Councillor addressed the Committee.

 

On a motion by the Chair and seconded by Councillor K Hodson it was –

 

Resolved (13:0) – That the application be approved subject to the following conditions:

 

APP/19/00535 - Variation of Condition 2 of APP/17/00183 to vary the approved plans, with the following amendments incorporated:

1. Hip-to-gable change on the proposed extension

2. Two new dormers included for Plot 18 (replaces one dwelling removed from Church conversion)

3. Zinc cladding to overcome mixture of materials used in original elevations.

4. Other internal alterations, as shown on plans, to suit complexities of working with the existing structure (including new dormer for landing on extension) - Hoylake Presbyterian Church, ALDERLEY ROAD, HOYLAKE CH47 2AX - Approve The development hereby permitted shall be begun before the expiration of 3 years from the date of this permission.

 

The development hereby permitted shall be carried out in accordance with the approved plans received by the local planning authority on 6th July 2017 and listed as follows: 477.001; 477.002; 477.003; 477.004; 477.005 and amended plans received on 8th April 2019 and listed as follows: 477.006 B; 477.007; 477.008 A; 477.009 B; 477.010 B

 

The external finishes of the development hereby permitted shall be as follows (and corresponding with the approved drawings) unless otherwise agreed in writing by the Local Planning Authority: · Bricks - Ibstock Ravenhead Red Smooth (Travis Perkins Product Code 860091); · ZINC

 

Prior to first occupation, the following windows shall be obscurely glazed and non-opening up to a minimum of 1.7m above finished floor level, and shall be retained as such thereafter: - All first-floor windows in the north-west elevation of the proposed extension; - The bathroom windows serving Plots 9 and 10; - The kitchen window serving Plot 9; - The west-facing windows in the oriel bays on the north-west elevation of the existing church (two windows, both serving Plot 10); - The dormer window on the north-west elevation of the proposed extension (serving a communal landing area)

 

The development hereby permitted by this planning permission shall be carried out in accordance with the approved documents:

· Sustainable Drainage Strategy <27/9/17 / CL7959 / SWF Consultants>. · Proposed Drainage Plan <APR2017/ CL7959-101/Rev P2/ SWF Consultants>

The approved scheme shall be implemented in accordance with the approved details and timetable.

 

No development shall commence until full details of a scheme for a surface water sustainable drainage system to serve the site, and method of implementation including arrangements to secure funding and maintenance for the lifetime of the development through an appropriate legally binding agreement have been submitted to and approved in writing by the Local Planning Authority in consultation with Lead Local Flood Authority.

 

The approved scheme shall be implemented in accordance with the approved details and timetable.  Thereafter the surface water sustainable drainage system shall be managed and maintained in accordance with the approved scheme.

 

No development shall commence until details of an appropriate management and maintenance plan, including arrangements to secure funding for the lifetime of the development through an appropriate legally binding agreement, for the surface water sustainable drainage system, comprising all components of the surface water drainage system, have been submitted to the Local Planning Authority, in conjunction with the Lead Local Flood Authority.

 

The plan shall be implemented in accordance with the approved details prior to first occupation of any of the approved dwellings, or completion of the development, whichever is the sooner. Thereafter the surface water sustainable drainage system shall be managed and maintained in accordance with the approved details.

Supporting documents: