BIRKENHEAD TOWN CENTRE MOVEMENT SCHEMES

Minutes:

The Lead Commissioner for Strategic Transport and Technology presented the report of the Director of Regeneration and Place, stating that the report provided an update on the Phase 1 consultation undertaken regarding the town centre movement schemes at Conway Street/Europa Boulevard and Grange Road Charing Cross/Grange Road West and sought approval to delegate authorisation to the Director of Neighbourhoods to consider the outcome of the Phase 2 consultation and make the decision regarding the implementation of the schemes.

 

The report also sought approval for the acceptance of a further allocation of £1,625,000 of Active Travel Tranche 3 funding to support the delivery of the Conway Street/Europa Boulevard scheme. The Conway Street/Europa Boulevard scheme and the Grange Road/ Charing Cross/Grange Road West projects are part of the council’s Future High Street Fund (FHSF) programme. The Conway Street/Europa Boulevard scheme also has an allocation of Active Travel Tranche 3 Funding.

 

The projects were both critical components of the regeneration of Birkenhead town centre, aiming to make the town centre more attractive through supporting improved accessibility and increasing active and sustainable travel movements.

 

Members queried various aspects of the scheme, raising some concerns as to schemes being dislocated and lacking in ambition, and were informed that an Active Travel Vision Document would be coming to Committee later in the year, and that a full detailed infrastructure plan was being developed. Members also noted that applications for grants needed to be in line with government policy ad criteria in order to be feasible. Members also shared frustration that the deadlines for applying for funding were tight, suggesting that there was less time for consultation.

 

Members discussed each scheme and car parking, asking if a full assessment for car parking spaces will be undertaken. Also considered was the impact of anti-social behaviour on the scheme as well as making the public realm dementia friendly.

 

A motion was then put by Councillor Max Booth, Seconded by Councillor Vida Wilson that,

 

In reference to option 2.1 and in light of the committee not seeing the phase two consultation results, the Director of Neighbourhoods is requested to seek an extension of time beyond the 31st of March 2024 funding deadline. This will accommodate for a time whereby the ECET committee can analyse the phase two consultation responses during the ECET committee meeting scheduled to take place on the 20th of September 2023

 

A vote was had and the motion was lost (4:8)

 

On a motion by the chair, seconded by Councillor Steve Foulkes. The motion was then voted on and agreed (8:4). It was therefore,

 

Resolved – that,

 

1. The outcome of the Phase 1 consultation regarding the Conway Street/Europa Boulevard and the Charing Cross/Grange Road/Grange Road West scheme and associated officer comments which are included with Appendix 1 – 4 of this report be noted;

 

2. Delegated authority regarding the implementation of the Conway Street/Europa Boulevard scheme and the Grange Road/ Charing Cross/Grange Road West scheme be given to the Director of Neighbourhoods, following consultation with the Ward Members, Chair and Spokespersons of the Economy, Regeneration and Housing Committee and the Environment, Transport and Climate Emergency Committee regarding the objections and expressions of support received during the Phase 2 consultation;

 

3. £1,625,000 of additional Active Travel Tranche 3 Funding to support the delivery of the Conway Street/Europa Boulevard scheme be accepted.

Supporting documents: