Resolved – That,

 

(1)  the acceptance of the additional £315,000 Key Route Network funding from the Combined Authority and its allocation to deliver the schemes set out in appendix 1 to the report, be approved;

 

(2)  the additional schemes set out in appendix 2 to the report, to be funded from the ‘Main (Classified) and KRN’ allocation previously approved by Cabinet in March 2019, be approved.

 

(3)  the programme of footway refurbishment and treatment schemes set out in appendix 3 to the report, and micro-asphalt surface treatment and patching schemes set out in appendix 4 to the report, to be funded from the remainder of the ‘Local (Unclassified) Roads’ allocation previously approved by Cabinet in March 2019, be approved.