Issue - decisions

Capital Programme 2021-26

05/03/2021 - CAPITAL PROGRAMME 2021-26

Resolved – That the recommendations contained within minute 69 of the Policy and Resources Committee of 17 February, 2021, be agreed in that the following be approved:

 

(1)  new bids as detailed in Appendix 2 to this report requiring £12.133 million borrowing for inclusion in the Capital Programme;

 

(2)  any new bids supported by grant funding do not commence until written confirmation has been received from the granting authority;

 

(3)  the Capital Programme 2021/26 (as detailed in Appendix 3 to the report);

 

(4)  that progress on delivering the Capital Programme will be presented in accordance within the agreed Capital Monitoring arrangements.