10/08/2022 - Installation of Mobile Classrooms at Hayfield School ref: 5075    For Determination

This report requests that the Interim Director of Regeneration and Place agrees to award a construction contract to Portacabin Ltd. The contract allows for a rental period for two mobile classrooms for a 104-week period which will enable an additional 40 Special Educational Needs and Disabilities (SEND) pupil places to be provided at the school.

Decision Maker: Director of Regeneration and Place

Decision published: 15/08/2022

Effective from: 19/08/2022

Decision:

Resolved – That the hire and installation of two mobile classrooms at Hayfield School be agreed with effect from 8 August 2022 to Portakabin Ltd in the total sum of £759,556 for a period of 104 weeks.


12/08/2022 - Appointment Of Design Lead For The Birkenhead Waterfront Programme ref: 5074    Recommendations Approved

Not for Publication by virtue of by virtue of paragraph(s) 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

Decision Maker: Director of Regeneration and Place

Decision published: 12/08/2022

Effective from: 12/08/2022

Decision:

Not for Publication by virtue of by virtue of paragraph(s) 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

 

Lead officer: James Hurley


29/07/2022 - Family Support - Family H ref: 5073    Recommendations Approved

As detailed within the report.

Decision Maker: Director of Children, Families and Education

Decision published: 11/08/2022

Effective from: 29/07/2022

Decision:

Resolved – That the recommendations as detailed within the report be agreed.

Lead officer: Colleen Halpin, Simone White


04/08/2022 - Future Health protection service ref: 5072    Recommendations Approved

Wirral’s existing Local Outbreak Hub is funded until 30th September 2022, by the Contain Outbreak Management Fund (COMF). 

 

This report seeks approval for the COMF grant to continue to fund the newly revised Health Protection Delivery Service for six months, from October 2022 until March 2023, when this funding stream will conclude, to ensure local resilience and continuity. The service will be evaluated throughout this period, to inform future plans.

 

The continuation of the local Heath Protection Service will contribute to the Wirral Plan Aims, in particular ‘Active and Healthy Lives’, supporting Wirral residents and communities to live safely with COVID-19 and protect the health of communities from infectious diseases and environmental hazards.

Decision Maker: Director of Public Health

Decision published: 04/08/2022

Effective from: 10/08/2022

Decision:

That Wirral’s Health Protection Delivery Service be funded from October 2022 to March 2023 through the Contain Outbreak Management Fund in the sum of £342,600.

Wards affected: (All Wards);

Lead officer: Jennifer Smedley