The Director of Children’s Services presented a report detailing the work that was required to provide a new primary school and demolition of the existing school at Park Primary School and the costs of the scheme.

 

Resolved - That

 

(1)  the Scheme and Estimate, as presented, be accepted;

 

(2) the Director of Technical Services be authorised to seek tenders for the project;

 

(3) the Director of Technical Services be authorised to obtain all necessary statutory approvals for the project.